Daily drilling reports · rig time

IADC daily drilling report codes, explained

IADC daily drilling report (DDR) codes are the standard numbers drilling crews use to classify every hour of rig time on the IADC daily report, or tour sheet. Code 2 is drilling, 6 is trips, 8 is rig repair, 12 is running casing and cementing, 19 is fishing, and so on. Since 2019 the IADC DDR Plus has 34 main codes: it keeps the 23 operational codes of the paper report, with minor clarifications, adds new ones such as operating status, safety and well control, and lets each code be broken down further into activity and equipment sub-codes. Because each code has defined start and stop points, the same 24 hours can be compared across rigs, wells and contractors, which is what makes lost time and nonproductive time measurable. These are not the same as IADC bit codes, which classify drill bits.

Reference summary only. The definitions below paraphrase IADC's published DDR Plus code definitions; use the current IADC documents and your contract's reporting requirements for the exact wording, sub-codes and rules.

1. What the IADC daily drilling report is

The IADC daily drilling report, often called the tour sheet, is the standard daily record of a drilling rig's work. It records the crew, depths, the bit and bottom-hole assembly, mud properties, pumps, casing, safety events and, above all, a time log: every period of the day, its start and end time, its code and a short description of what was done. Drilling contracts commonly use it as the basis for agreeing what happened on the rig and how the time is paid, so the time codes matter to the contractor, the operator and the accounts team, not only the driller.

IADC introduced the DDR Plus in March 2019. It kept the legacy operational codes with minor clarifying changes and added new top-level codes, giving 34 main codes. Each main code can cascade into an activity, an activity sub-code, an equipment code and an equipment sub-code, so a report can say not just "rig repair" but which piece of equipment failed. IADC also published an electronic schema for the report, based on the Energistics WITSML data-transfer standard, so reports can move between systems without retyping.

2. The main IADC DDR Plus codes

The table summarises the main codes and their start and stop points, paraphrased from IADC's DDR Plus definitions document.

CodeOperationWhat it covers and when it starts and stops
1Rig up / tear down / rig moveFrom the first rig components arriving on site until the rig is ready to spud; tear down runs until the last component has left. Offshore rig moves are included.
2DrillingMaking new hole. Starts when boring begins and ends when it stops. Also used for drilling out shoe tracks and dressing off cement plugs.
3ReamingSmoothing or enlarging the hole, straightening doglegs or helping directional work; from the start to the end of rotating and circulating for that purpose.
4CoringCutting a cylindrical rock sample for geological analysis.
5Circulate & condition mudAdjusting mud properties such as weight and viscosity and circulating; from blending additives until circulation is complete and the pumps are off.
6TripsRunning or pulling the BHA to or from a depth, including wiper and check trips to test hole condition, tight spots or mud weight.
7Service / maintain rigPlanned maintenance, whether time-, condition- or usage-based; from taking the equipment off line until it is back in service.
8Repair rigReactive repair of unexpected equipment failure that stops operations; from the failure until the equipment is back in service.
9Replacing drill lineSlipping and cutting or replacing drilling line, from removing the drawworks from service until it is returned. See ton-mile calculation.
10Deviation surveyMeasuring borehole trajectory on the critical path.
11Wireline logsFrom assembling and running the logging tools until they are fully retrieved.
12Run casing & cementFrom rigging up casing equipment until the last of the cement is in place.
13Wait on cementFrom shutting down the cement pumps until tests show the cement has hardened enough.
14Rig up / down BOPAssembling a surface (dry) BOP stack until it is installed and ready to use or test.
15Test BOPFrom the start of function and pressure testing until all measurements are made and approved.
16Drill stem testFrom picking up the test packers until all tools are out of the hole.
17Plug backFrom running the plug or cement head until the tools are back at surface.
18Squeeze cementFrom rigging up squeeze equipment until it is rigged down.
19FishingFrom picking up the fishing assembly until it is back at surface.
20Specialised directional workWork with a directional assembly when deviating from the primary wellbore; otherwise directional drilling falls under code 2 sub-codes.
21–23OtherUser-defined operations not covered by another code.
31Run / retrieve riser equipmentOffshore: moving the BOP and marine riser to and from well centre.
32Surface testingTesting well-related surface equipment, such as the choke or standpipe manifold, while it holds up other work.
33Operating statusPeriods when the rig is not performing well operations, such as standby, from one change of status to the next.
34SafetySafety meetings, training, stand-downs, job safety analyses and drills.
35Well controlActions taken to return the well to a safe state after a loss of hydrostatic control. See kill sheet calculations.
36Coiled tubingFrom running the coiled tubing in the hole until it is fully retrieved.
37Completion activitiesPerforating, tubing trips, treating, swabbing and testing.
38Subsea installationsSubsea work, which varies by situation.

Codes 21 to 23 are deliberately open, so a contractor or operator can define its own categories for work that has no standard code. Agree what they mean at the start of the contract, otherwise "Other" becomes the place where unexplained hours collect.

3. Why start and stop rules matter

The value of the codes is that everyone draws the line in the same place. A trip under code 6 starts when the crew picks up or starts pulling the BHA and ends when it reaches the target depth or is laid down. Waiting on cement under code 13 starts when the cement pumps stop, not when the cement job was planned to finish. Rig repair under code 8 starts at the moment of failure. With defined start and stop points, the hours for each activity can be totalled and compared between rigs, wells and contractors: how long trips take per thousand feet, how much time goes to BOP testing, or how many hours a month are lost to repairs.

4. Productive time, lost time and NPT

The codes do not, on their own, say whether time was productive. That depends on whether the work was planned. Drilling, planned trips, casing and cementing, logging and BOP tests are normally part of the well plan. Time spent dealing with something that went wrong is usually counted as nonproductive time (NPT). Typical examples:

DDR Plus added a dedicated nonproductive-time category and equipment sub-codes so the cause can be recorded at source. Whatever system a company uses, the rule is the same: log NPT with a cause, the equipment involved and who was responsible, at the time it happens, so that it can be analysed later and, where the contract says so, charged at the right rate.

There is also time that never shows up as NPT because the operation was planned: a trip that took twice as long as it should have, or slow connections. That is often called invisible lost time, and it can only be found by comparing coded durations against a benchmark, such as the same operation on previous wells. For NPT formulas, a worked example and ways to reduce it, see NPT in drilling, explained.

5. Common daily drilling report errors

6. In DrillX

DrillX daily drilling reports use IADC-style time logs. DrillX checks each report as you type, flags lost time and catches errors such as depth at 24:00 shallower than at 00:00, or footage with no drilling time logged. The rig fleet view shows each rig's latest position from its daily report, and NPT insights show where rig time is being lost. DrillX also includes calculators such as a kill sheet, ECD and string volumes. DrillX opens soon; email info@drillx.app for a demo or early access.

Questions

What are IADC DDR codes?

IADC DDR codes are the standard time codes on the International Association of Drilling Contractors' daily drilling report. Each hour of rig time is logged against a numbered code, such as 2 for drilling, 6 for trips or 8 for rig repair, so that rig time can be totalled and compared in a consistent way across rigs, wells and contractors.

How many codes are in the IADC DDR Plus?

The IADC DDR Plus, launched in March 2019, has 34 main codes. It keeps the 23 legacy operational codes with minor clarifying changes, adds new codes including operating status, safety, well control, coiled tubing and subsea installations, and breaks each code down into activity and equipment sub-codes.

What is the difference between code 7 and code 8 on the IADC report?

Code 7, service and maintain rig, is planned maintenance done to keep equipment working. Code 8, repair rig, is reactive: it starts when equipment fails unexpectedly and ends when it is back in service, and it normally sits on the critical path, so it is usually counted as lost or nonproductive time.

Are IADC DDR codes the same as IADC bit codes?

No. IADC bit classification codes describe drill bits, for example a three-digit code for roller-cone bits by formation hardness and bearing type, and IADC dull grading describes bit wear. DDR codes classify rig time on the daily drilling report.

How is nonproductive time recorded on the IADC report?

Time spent on unplanned events, such as rig repair, fishing for lost equipment or regaining well control, is logged under the matching code and usually flagged as nonproductive. IADC's DDR Plus also added a dedicated nonproductive-time category and sub-codes for the activity and equipment involved, so the cause can be analysed later.

Do the hours on an IADC daily report have to add up to 24?

Yes. A daily report covers the full day, so the time log for each 24-hour period should total exactly 24 hours, including waiting, standby and other non-drilling time. Gaps or overlaps are one of the most common reporting errors.